What notification period is required by OPM to inspect pesticide application records?

  1. No notice is required

  2. 12-hour notice is required

  3. 24-hour notice is required

  4. 48-hour notice is required

The correct answer is: 24-hour notice is required

The correct notification period required by the Office of Personnel Management (OPM) for inspecting pesticide application records is 24 hours. This timeframe allows for adequate preparation and ensures that all necessary records are accessible for review. A 24-hour notice strikes a balance between giving enough time to prepare while maintaining efficient oversight of pesticide application practices. This level of notice is important for regulatory compliance, as it helps ensure that all documentation is available for inspection and that any relevant personnel can be present to provide insight or clarification during the review process. Having this structured notification period fosters accountability and transparency in the management of pesticide applications, which is crucial for environmental health and safety.